Projects: INDUSTRIAL DIVISION & SERVICES - ARGENTINA
-
25 Process Tanks. TOTAL AUSTRAL S.A. Cerro Vanguardia. Santa Cruz
Client: TOTAL AUSTRAL S.A.
Scheme: JV with AESA S.A.
Year: 2001
Manufacture, provisions, assembling and tests of 25 process tanks (aprox. 670t), 4 condensation tanks (aprox. 550t) and 2 stripping towers (aprox. 3.2m, height 30m, unit weight 47t). -
Gas Plant. PETROBRAS S.A. North Yac. Chango I. Salta
Client: PETROBRAS S.A.
Scheme: JV with AESA S.A.
Year: 2005
Mechanical Cooling Unit. Process capacity of 2,0Mm3/day. Basic and detailed Engineering. Civil construction. Supply of systems and process modules. Electrical and mechanical set-up. Tests and commissioning -
LPG Separation Plant. CAPEX S.A. Yac. Agua del Cajón. Neuquén
Client: CAPEX S.A.
Scheme: JV with AESA S.A.
Year: 2002
Turn Key Project. LPG Separation by Turbo Expansion Plant. Basic Engineering combined with detailed Technology. Manufacture and Supply of systems and process modules. Civil construction. Electrical & Mechanical Setup. Tests and commissioning. -
Gas Plant. TOTAL AUSTRAL S.A. Yac, Loma de La Lata. Neuquén
Client: TOTAL AUSTRAL S.A
Scheme: JV with AESA S.A.
Year: 2004
Turn Key Projects. Mechanical cooling Unit. Basic and Detailed Engineering. Supply of systems. Civil construction. Electrical and Mechanical Setup. Tests & commissioning.
Photo Gallery
We offer the following pictures that belongs to these projects. You can see the image enlarged clicking on the thumbnails.